MARSHLAND SCHOOL CHRISTCHURCH

Background

MultiMedia Communications were contracted with City Care working on Stage One of the Marshland School build.

Time Frame

The MultiMedia Communications team began working on this project in July 2015 and was successfully completed on time and on budget in March 2016.

0

metres of Molex cat6 cable

0

data Outlets

0

data cabinets

0

metres of air blown fibre optic cable

MMC INVOLVEMENT

This Marshland School project included all the Communications cabling, which have had 5x data cabinets with over 350 data outlets in place and have totally consumed over 18000 metres of molex cat6 cable connected with 500 metres of air blown fibre optic cable. We also have installed full PA system with local zone inputs and AV cabling.

Outcomes

This was a highly rewarding project that MMC completed on time and on budget and it was so successful that MMC picked up stage 2 of the build which included 2 x more Hubs.

TOP